on 03-08-2013 4:17 AM
Hi PS Guru,
I have created workforce planning profile and project with network and activities add work center and activity, then execute CMP2 but getting error.
Message no. C#043
Regards,
Aryan
Hi,
As Tushar has mentioned above, check if the work center that you are using has Capacities defined. Also, have you defined any work in hours for the activity?
You can also check your workforce planning profile and if required do necessary changes to resolve this.
Revert with your findings.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aryan,
Is work center added in the activity have Capacities defined.
Also check if Calculation key is maintained in the activity as ' Calculate Work'
Check few points mentioned in below thread as well
https://scn.sap.com/thread/1628637
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi tushar,
in workcenter capacity tab cap category is 0002 = person and other formula SAP008, int distribution key is SAP020
in workforce profile
Wrkfrc plan. profile Z000000001 == Project workforce profile
planing period
Date type G No. of calender day
Start date 0 Factory Calendar ID = [ ]
Finish date 60 Fiscal Year Variant V3 = [V3]
display
Period unit A day [check] = mixed period types
Period width 4 availability
[✓] = work to distribute/distributed work x = display availability cap
[✓] = display netowrk x = display total load
disaggregation assignment allowed
O = work to period start x = other personal resource
activity work distribution in % load on the person in &
Display Display
red 0.00 < 50.00 @ green 0.00 <100.00 @
yelow > 50.00 < 90.00 @ yelow>100.00 <125.00 @
gren > 90.00 @ red>125.00 @
period split folder
no. period unit no-period
1 A Day 7
2 A Day 30
3 C Week 4
4 D Month 1
Regards,
Aryan
Hi tushar,
in workcenter capacity tab cap category is 0002 = person and other formula SAP008, int distribution key is SAP020
in workforce profile
Wrkfrc plan. profile Z000000001 == Project workforce profile
planing period
Date type G No. of calender day
Start date 0 Factory Calendar ID = [ ]
Finish date 60 Fiscal Year Variant V3 = [V3]
display
Period unit A day [check] = mixed period types
Period width 4 availability
[✓] = work to distribute/distributed work x = display availability cap
[✓] = display netowrk x = display total load
disaggregation assignment allowed
O = work to period start x = other personal resource
activity work distribution in % load on the person in &
Display Display
red 0.00 < 50.00 @ green 0.00 <100.00 @
yelow > 50.00 < 90.00 @ yelow>100.00 <125.00 @
gren > 90.00 @ red>125.00 @
period split folder
no. period unit no-period
1 A Day 7
2 A Day 30
3 C Week 4
4 D Month 1
now let me know what should i do??
Regards,
Aryan