I have created workforce planning profile and project with network and activities add work center and activity, then execute CMP2 but getting error.

No requirements were found for the selection criteria

Message no. C#043

Regards,

Aryan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As Tushar has mentioned above, check if the work center that you are using has Capacities defined. Also, have you defined any work in hours for the activity?

You can also check your workforce planning profile and if required do necessary changes to resolve this.

Revert with your findings.

Regards,

Gokul

Former Member
0 Kudos

Hi Aryan,

Is work center added in the activity have Capacities defined.

Also check if Calculation key is maintained in the activity as ' Calculate Work'

Check few points mentioned in below thread as well

https://scn.sap.com/thread/1628637

Regards

Tushar

Former Member
0 Kudos

Hi tushar,

in workcenter capacity tab cap category is 0002 = person and other formula SAP008, int distribution key is SAP020

in workforce profile

Wrkfrc plan. profile    Z000000001  ==  Project workforce profile

planing period
Date type           G No. of calender day
Start date             0                   Factory Calendar ID       =   [ ]
Finish date          60                  Fiscal Year Variant  V3    =  [V3]

display
Period unit            A day                   [check] = mixed period types
Period width         4                                                             availability
[✓] = work to distribute/distributed work                      x = display availability cap
[✓] = display netowrk                                                     x = display total load

disaggregation                                                               assignment allowed   
O = work to period start                                             x = other personal resource

activity work distribution in %                       load on the person in &
                                         Display                                              Display
red       0.00     < 50.00         @         green   0.00      <100.00         @
yelow > 50.00  < 90.00         @        yelow>100.00   <125.00         @
gren   > 90.00                        @          red>125.00                             @

period split folder
no.            period unit   no-period
1               A Day              7
2               A Day              30
3               C Week           4
4               D Month          1

Regards,

Aryan

Former Member
0 Kudos

Hi tushar,

in workcenter capacity tab cap category is 0002 = person and other formula SAP008, int distribution key is SAP020

in workforce profile

Wrkfrc plan. profile    Z000000001  ==  Project workforce profile

planing period
Date type           G No. of calender day
Start date             0                   Factory Calendar ID       =   [ ]
Finish date          60                  Fiscal Year Variant  V3    =  [V3]

display
Period unit            A day                   [check] = mixed period types
Period width         4                                                             availability
[✓] = work to distribute/distributed work                      x = display availability cap
[✓] = display netowrk                                                     x = display total load

disaggregation                                                               assignment allowed   
O = work to period start                                             x = other personal resource

activity work distribution in %                       load on the person in &
                                         Display                                              Display
red       0.00     < 50.00         @         green   0.00      <100.00         @
yelow > 50.00  < 90.00         @        yelow>100.00   <125.00         @
gren   > 90.00                        @          red>125.00                             @

period split folder
no.            period unit   no-period
1               A Day              7
2               A Day              30
3               C Week           4
4               D Month          1

now let me know what should i do??

Regards,

Aryan

Former Member
0 Kudos

Hi Aryan,

Check whether resources are assigned to Work center.

Also check settings of Capacity requirement in configuration of Control key in OPSU.

Compare your workforce planning profile settings with standard profile 1302.

Regards