Need to remove planning total (budget amount) from order

I have an internal order created from an appropriation request that needs to be rejected/canceled and a new request

created as a project.  I have created the new project and now need to distribute the budget.  How do I remove the order

from the budget dollars planning total?  What Tcode do I use to get down to the order not just the position?  I have tried IM22

but I get this error "60001188 has to remain assigned to a program position".

Thanks, Tonya

Former Member
Not what you were looking for? View more on this topic or Ask a question