Can someone explain, what are the activities of Go-live, w.r.to PI.
Thank you very much sunil and Raja Sekhar for your valuable inputs..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1)First you need to create a task for each and every interface befre go live, that task should be authorized from CutOver team who send a notifictaion to check interface readiness .i.e all interface developments are tranposrted to productrion and configurtaions maintained correctly.
2)Performing a smoke test: Some cases other teams wannt to perform smoke before go live, it gauratees that all interfaces working. So here bussines has to involve to send real busines strasaction data , this is optional but can be done before go live.
3)Checking connectivty to all systems : You need to validate all PI connectivty points and make sure that everything working .
4)Once System Go Live happens then routine PI monitoring activities....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is more of project specific.
> Roughly, first and foremost it should have readiness check, follow SAP Note # 817920 - PI Readiness Check based on your version,
> Documentation
Standards, Procedures & Guides
Quality Documents
> End User Training
> Cut Over & Go-Live
Detailed Go-Live and Cutover plans
Customizing setting & repository object transportation on PRD
> Hyper care and Post Go-Live Support
You may refer this document from technical perspective..
SAP PI Implementation Methodology..
Regards,
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.