PI Go live activities

Bhargavakrishna
Active Contributor
0 Kudos

Hi Experts,

Can someone explain, what are the activities of Go-live, w.r.to PI.

Accepted Solutions (0)

Answers (3)

Answers (3)

Bhargavakrishna
Active Contributor
0 Kudos

Thank you very much sunil and Raja Sekhar for your valuable inputs..

rajasekhar_reddy14
Active Contributor
0 Kudos

1)First you need to create a task for each and every interface befre go live, that task should be authorized from CutOver team who send a notifictaion to check interface readiness .i.e all interface developments are tranposrted to productrion and configurtaions maintained correctly.

2)Performing a smoke test: Some cases other teams wannt to perform smoke before go live, it gauratees that all interfaces working. So here bussines has to involve to send real busines strasaction data , this is optional but can be done before go live.

3)Checking connectivty to all systems : You need to validate all PI connectivty points and make sure that everything working .

4)Once System Go Live happens then routine PI monitoring activities....

smavachee
Active Contributor
0 Kudos

It is more of project specific.

> Roughly, first and foremost it should have readiness check, follow SAP Note # 817920 - PI Readiness         Check based on your version,

> Documentation

   Standards, Procedures & Guides

   Quality Documents

  

> End User Training

> Cut Over & Go-Live

   Detailed Go-Live and Cutover plans

   Customizing setting & repository object transportation on PRD

> Hyper care and Post Go-Live Support

You may refer this document from technical perspective..

SAP PI Implementation Methodology..

Regards,

Sunil