Hi All,

I am working on Inter company STO process and i am referring Std schema RM0000 with PB00 &PBXX condition types , i have added one more condition record for ZP01 (supplyin plant+vendor ) and have mentioned the Transfer price (say in USD) and have assigned this to access sequence

this access sequence is assigned to new condition type ZPTP and have included the same in Pricing procedure with step 1 and counter 0 which is followed by PB00 &PBXX

1     0          ZPTP    

Still i am unable to determine the transfer price and i am getting error

"Net price must be greater than 0"

Regards,

Preeti.pg