on 02-27-2007 3:20 PM
Hi All:
SAP recommends to change MRP type for materials to XO or similar, when planning the material in SNP/ PPDS. I was wondering does changing to MRP type XO affect ATP processing?
Thank you
Mono
IT does not affect the ATP check directly... You will require to do proper ATP check related settings e.g. Chckging groups and control.