on 03-05-2013 7:38 AM
I would like to write a Rule that If Production Order is confirmed in SAP then through EM an E-Mail will be sent to MRP controller.
How to write this Rule Set in EM?
What will be the syntax.
thanks
A Prasad
Hello Prasad,
normally you have then an event for Production Order is confirmed. In the rule set you can check with activity EVENT_CODE_CHECK if this event happened and then trigger the alert framework.
There are many examples in the delivered scenarios just check e.g. rule set:
TRA10
-> rule EMAIL_CUSTOMERS
multi task activity TRA10_DELAY_ALERT
Best regards,
Steffen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for reply.
Can you please tell me the step by step process of how to write a Rule Set.
Or if you have any doc, plz mail me to ppuser@rediffmail.com
Regards
prasad
Hi Prasad,
just go to transaction /SAPTRX/TSC0TR there are many examples also the one mentioned above.
General infos you can find here:
http://help.sap.com/saphelp_tm80/helpdata/en/33/49583c2e39e433e10000000a114084/frameset.htm
Best regards,
Steffen