on 03-04-2013 10:05 AM
Hi Basis Expert,
We have 4 system landscape namely DEV, QAS, Pre-Prod & PROD.
Now we have done TMS configuration of DEV, QAS & Pre-Prod choosing Three System Landscape.
Going forward during Go Live we will also have to add Prod system in the landscape.
Please let me know how can we configure TMS with four system landscape DEV,QAS,PRE PROD,PROD.
Regards,
Anil
hi anil.
Please check the below link in which explained the configuration steps of STMS .
http://www.sapbasismania.net/2012/11/how-to-configure-sap-transport-route.htmlSTMS Configuration
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please follow the below link . It will help you
http://help.sap.com/saphelp_nw70/helpdata/en/44/b4a0c17acc11d1899e0000e829fbbd/content.htm
Thanks and Regards,
Vimal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Simply add a delivery route to your production system. Nothing else.
Regards, Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.