Use resource with Time Bucket Profile

Former Member
0 Kudos

Hi All Experts

I created Resource in APO using TA RES01.

and then when I trying to create PPM in APO and attached my own created Resources in Mode select the resource, it is showing error

"Use a resource with Time Bucket Profile -> resource"

Would you please let me know how to solve this.

Regards

Tapan Paul

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Tapan,

It would help if you provided some more information such as how you created the resource and what type of PPM you are trying to create.

Using my crystal ball, I'm going to guess that you are trying to create an SNP PPM which requires bucketed resources.  If that is the case, then the resource you created to support the PPM was probably created as a single or multi type resource.  The resource should be created as a single-mixed or multi-mixed resource.  In a mixed resource, you can set it so that the time buckets are derived from the time-continuous capacity.  Ensure that you have added the resource to the model which adds it to all of the planning versions.

Best Regards,

Mike

Former Member
0 Kudos

Hi Mike

Resource I created was not single mixed or multi mixed,

that was the problem. Now I created single mixed resource and it solved.

Thanks So Much.

Best Regards

Tapan Paul