cancel
Showing results for 
Search instead for 
Did you mean: 

Reversal of J1IF13

former_member223868
Participant
0 Kudos

Dear Experts

I have complete one subcontracting challan (J1IF13) now its status is 'C'. But there is some mistake and i want to change its status 'P' post.

Please advise is this possible.

Case is- I reverse one challan and when received material i did not reconcile it and recredit w/o reconcile this challan and  complete it. Due to this i could not get Excise benefit back. Now i want firSt reconcile it and then will complete with recredit.

Regards

Parkash

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Try changing status in above tables as it is the only way around, if you want to proceed with.

Former Member
0 Kudos

Hi

Parkash,

Now the alternative is change the status of the challan at the excise

table level in table J_1IEXCDTL, J_1IEXCHDR.

Pls try if this helps in your test or dev system first.

Regards,

Rajasree