on 02-28-2013 9:22 PM
Hi,
We have a scenario where product is valid on 2 transprtation lanes.
There is a overlap of validity based on lead times from different sources.
e.g. Source DC1, DC2 Destination is : PORT
Lane DC1-->PORT is valid from 01/01/2013 to 26/10/2013
Lane DC2-->PORT is valid from 24/09/2013 to 31/12/9999
If we go into interactivbe planning book and try to create manual order then I get a pop up screen to select source from available 2 options, if the requirement date is falling under any overlap period.
e.g. If I enter a order for Oct 5th, then I get both options and need to select one of those.
My question here is how the source determination happens when we run background heuristics planning?
Is there any criteria which we can define for source determination?
Thanks
in advance for your help!
Thanks
Yogesh
Hi Yogesh,
SNP heuristics uses the following criteria in determination of source of supply. Please note that the available sources of supply must be valid during the period of consideration.
Please check the following link for details.
http://help.sap.com/saphelp_ewm70/helpdata/en/da/8df3128121304a8dc1eef961a6d3a8/frameset.htm
Thanks,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajesh,
Thanks for your quick reply!
I understand and agree with above mentioned criteria.
In our case we do not have quotas or priorities or cost factors, there are 2 lanes valid for 5 weeks of overlap period. In this scenario, during heuristics run which source gets selected.
In interactive planning, I can see 2 options when I try to create SNP Purchase req.
But in background planning which source gets priority?
Appreciate your help!
regards
Yogesh
Hi Yogesh,
Considering all the factors same, any transportation solve/algorithm picks the route/t.lane with shortest distance or duration. If the distance/duration also equal, then the choice is random.
Assumption: There is no special form or relationship type (i.e. scheduling agreement or contract or consignment) of external procurement is involved.
Thanks,
Rajesh
Thanks Rajesh,
I created 2 different scenarios but in 1 case its taking shortest distance source and other case longest distance source.I thought if its going by alphabetical order but that is also not the case.
That's why I got confused but seems that it's a random selection.
Just in similar note, for in house production suppose if there are 2 PDS valid with overlap validity then is it again a random selection?
Thanks
Yogesh
Hi Rajesh,
I just came across another issue related to tramsportation lanes. My understanding is the validity dates (maintained in each product om lane) are for receipts at destination location.
e.g. If Product is valid from 01/01/2013 till 30/06/2013 on source DC1and
Valid from 01/07/2013 till 31/12/9999 on source DC2
(destination is same), bith lead times are 3 weeks
Then system should create receipt from DC1 till 30/06/2013 and then from 01/07/2013 onwards, it should create receipt from DC2.
What is happening in my scenario is there are receipts from DC1 till 30/06 2013 but DC2 receipts are coming after 3 weeks gap.
Means there are no receipts for July 1st and 2 week. If I try to create a mnaul receipt then system shows the message 'Not possible to create order, start date is not in SOS validity'
Se seems that its looking start date as DC2.
Please suggest!
Thanks
Yogesh
Hi Yogesh,
The product specific t.lane validity date range is applicable to product and t.lane combination i.e. for a given product, the selected t.lane can be used during the specified date range. The external procurement order's start and end dates must fall within this date range. Otherwise, system does not recognize this t.lane as a valid source of supply for the order.
Thanks,
Rajesh
Thanks Rajesh,
Actually we don't have product specific T lanes scenario.
Let me give here simple example.
Suppose the validity is from 01/01/2013 to 31/12/9999 and lead time is 4 weeks.
If there is a demand in 2nd week of jan (10/01/2013), when will SNP heuristis propose a PR?
End date as 10/01/2013 and going back 4 weeks , aorund 12/12/2012 (which is before validity start date) OR the propose pR will be from 01/01/2013 with end date 28/01/2013.
my main question is what is the standard behaviour in SNP heuristics?
Does it create SNP stock transfer before validity start date of SOurce of Supply?
Thanks for your help!
regards
Yogesh
Hi Yogesh,
Consider the following example.
T.lane valid from 4/1/2013 - 12/31/9999
SNP heuristics execution:
The planning engine creates a proposal with starting date from April 1, 2013.
As you see in the above screenshot, the demands before 4/1/13 are grouped together and the sum considered for the replenishment along with usual target stock level.
I hope this live example will clarify your queries.
Thanks,
Rajesh
Hi Yogesh,
You can update the start date of an external procurement order manually and still use the same t.lane that is not valid on the start date of the order. Probably, you can delete the PReq that you mentioned in your post and replan the stock transfers using heuristics. This time, the heuristics will consider the t.lane validity periods.
It also be helpful to have system release and service package data
Thanks,
Rajesh
Hi Rajesh,
Thanks for the help!
I just have 1 last question in this regard:
I am seeing different behaviour in our QA and Production systems.
e.g. If T Lane is valid from 01/01/2013
Demand is on 15/01/2013 and lead time is 30 days then :
In QA, system doesn't allow to create receipt before start date of Source of Supply (T lane validity for product), means receipt was created with start date as 01/01/2013 and end date as 30/01/2013
So from Jan 15th to Jan 30th , I was in shortage.
In Production system, system created a receipt with start date as 15/12/2012 (wend beyond validity in past) and end date as 15/01/2013, so exactly match demand withut any shortage.
My question is, which is the standard SAP behaviour? There could be some notes mising or extra in either system so want to know which one is standard?
Thanks again!
Thanks
Yogesh
Hi Yogesh,
There might be some change in your QA and Production boxes. Pl compare the system release levels and implemented SAP notes of these two systems.
The following SAP notes might be useful:
Note 1450680 - SNP Heuristic: Wrong validity start for sources of supply
Note 1462773 - SNP Heuristic: Wrong scheduling for stock transfer orders
Note 1685896 - Start Date in the Past in SNP-Heuristic Planning
Note 1638031 - Start date of SNP stock transfers is not in SOS validity
Note 1292483 - Start Date in the Past
Thanks,
Rajesh
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.