on 02-28-2013 3:16 PM
Dear ps experts,
I am getting this error one project in PROD
Project getting assigned values in CJ31 Budget is 498,753,175 and assigned value is 127,907,382.29
And also Extra > availability control > analysis (assigned value = 127,907,382.29)
But in budget report S_ALR_87013558 assigned value is 194.962.298.
I run CJEN, CJBN, RKANBU01 but still problem is as it is.pl see screen shots
kindly help me very urgent basis
BR
prasad
Message was edited by: Mohamed Rafi - Do not use words like very urgent.
Message was edited by: Mohamed Rafi - Do not user words like very urgent.
Message was edited by: Mohamed Rafi - Do not user words like very urget.
Dear Prasad,
can you provide me the commitment details breakup, from t code s_alr_87013537.
Regards
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello Prasad,
Your Assigned costs in CJ31 ( 127,907,382.29) is less than your Actual costs in reporting ( 194.962.298) independent on the commitment value....
I think you need to retrieve all values that are in CJ31 that belongs to the assigned value and compare with values that are in actual costs reports ( example CJI3)... try to identify the missing entries in CJ31 to check why you have costs that are not being assigned.
regards
Hello Prasad,
Check value category customizing. You can refer below mentioned thread showing if there is inconsistency in RPSCO table.
http://scn.sap.com/thread/1555500
Regards
Tushar
Dear Prasad,
There is no screenshots...
Also in addition to above inputs, I would suggest you to refer Note 178837 - Availability control: Incorrect assigned value? showing what are the possible reasons of showing incorrect assigned values and possible corrections.
You can refer below mentioned thread where little similar type of issue has been discussed.
http://scn.sap.com/thread/1224371
Regards
Tushar
Dear Tushar,
Basis process leave it .we are discussion only about budget reports cj31 & s_alr_58
1)Project getting assigned values in CJ31 Budget is 498,753,175 and assigned value is 127,907,382.29And also Extra > availability control > analysis (assigned value = 127,907,382.29)But in budget report S_ALR_87013558 assigned value is 194.962.298.( I run CJEN, CJBN, RKANBU01 and before ur advised tick plng ind ( OPSC , OPSV, ) ts scenario also tested still my not solved .
2.) I am facing problem is Our user was trying to post project expenses in FB50 for 8800/- by selecting cost object as a WBS element system is showing the error that budget is exceeded for 75.884.193,29 /-. For your reference I am sending the below error screen shot And Budget report the system is showing budget availability for 303.773.168 /-. The report T.code is s_alr_87013558.
kindly suggest
BR
prasad
Hi Prasad,
I have checked the screeshots you have added in your other post, and you are right. At least in assigned value it seems that the report is taking you twice the costs in the low level WBS, when really they have already been assigned to the superior WBS.
I hope you can have a solution from SAP,
Regards
Hi all,
First, this behaviour is described in SAP note 1414563. It should provide you the reasons that contributed to the differences in both CJ31 and S_ALR_87013558. You would need to adjust the report definition. Please see my early thread:
http://scn.sap.com/thread/3171879
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Prasad,
This is due to incosistency of avialability control , And these can be resolved by applying Budget Commitment correction notes:
1. Please have a look at consulting note 1424698 which dealswith the potential reasons for exceeded budgets and how toavoid budget overruns in the future.
(2) Implement the corrections of the following notes, all dealing with severe availability control errors and not yet contained
Please check the following SAP Notes were avaialble in your current System or not , If not these SAP Notes has to be implemented to rectify the incosistencies.
In your current support package SAPKH60405:
1024884, 1038917, 1160142, 1412932, 1464000, 1495651, 1512987,
1532494, 1532773, 1543738, 1594484, 1606591, 1671565, 1681468,
1703755, 1719881,
(3) After the implementation of these notes, please reconstruct,availability control assigned values for all projects,by running txns CJEN and CJBN in background.
Caution: Do not start CJBN unless CJEN has finished.
Regards,
VRKUMAR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Prasad,
These are data Incosistency errors, Some times Project Committment tablee will not be updated.
So please try to run these Rectification Programmes:
1. RLORD035 : This Will deletes any duplicate PR or PO , where Budget Commitment has been Blocked.
2. RKANBU01: This Programme is an PR & PO Correction Programme to rectify the wrong Commitments.
After running these Programmes, Try to run CJEN and CJBN .
And after running these programmess also the incosistency value .
Regards,
VRKUAMR
Hello,
Check Extra > availability control > analysis the customizing settings --> It is possible you have cost element exempts in the AVAC that are being taking in account in the report.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.