Can we set System Date back-dated...

Former Member
0 Kudos

Hi,

We are making initial entry of some material data, as we are started go-live phase.

We want to make back-dated entry for initial stage. Can we set System Date back-dated ?.

Yusuf.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Cancelled Query. Date cannot be changed.

former_member204746
Active Contributor
0 Kudos

I agree with Ammey,

changing system data in a SAP system is looking for trouble.

You are trying to fix a functional issue with a bad Basis fix.

Ask your functionals to sort this out themselves.

Former Member
0 Kudos

Hello Yusuf,

Please think of some different work around. Probably you could take help of ABAPer's

Do not back-date the system. The results could be dangerious.

Regards,

Ammey Kesarkar