Hi,

I have created sampling procedure & DMR rule but in cannnot make relationship between it. It gives following error,Please guide regarding this problem.

Regards,

Avi

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Its very simple ....

You have used Sevarity 001 with AQL level  0,001.

You must maintain Sevarity 001 in DMR  and same should be selected in the sampling procedure with sampling scheme which has Sevarity 001 with AQL level  0,001.

or Vice versa.

Then you will be able to establish the relation.

Former Member
0 Kudos

Hi Avi,

In your sampling procedure in the additional data pop-up titled "Reference To Sampling Scheme" it is possible you have created an entry with a severity and AQL Level that is not present in your sampling scheme.  They must match up.

You can create entries in your sampling scheme for different combinations of inspection severity and AQL level.  That combination entered in your Sampling Procedure must be present in your Sampling Scheme

former_member211618
Contributor
0 Kudos

Hi,

   By using T.code QDB1 you can maintain relation between sampling procedure & DMR.