Scheduling in PS through Project Planning Board

Former Member
0 Kudos

Dear friends

I was doing scheduling in PS-Project Planning Board for one of our Projects. I would like to know is it possible to update the actual progress in activities in project planning board, based on the service entry done on ML81N. For normal scheduling we have to wait till one activity to get completed. By this way progress in between cannot be assessed.

with rgrds

Pradeep Madhavan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Post a partial confirmation against the NWA with a POC value.

Makal
Active Contributor
0 Kudos

Hi Pradeep,

Read SAP help. It gives all the information you want and also do little search the forum before posting the questions.

Regards,

Amaresh Makal