Manual material reservation as commitment

ricardo_mano4
Participant
0 Kudos

Manual material reservation as commitment

I would like to see on PS cost reports the value of a manual material reservation for WBS element as commitment. Does someone know if it is possible?

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Not possible in standard  SAP.

Regards,

Mahendra

Answers (2)

Answers (2)

ricardo_mano4
Participant
0 Kudos

Mahendra and Gokul

Thanks for your quick answer.

Best Regards.

Former Member
0 Kudos

This is not possible in standard SAP. Reservations, no matter how they are created are not treated as commitments in the standard SAP system.