Dear Expert,

After Running SNP optimizer ,  APO create orders in daily basis as result from finite capacity

During the PP/DS Run apo delete all this orders and create one order to cover the demand

My Issue is :

If you use optimizer to make cross finite planning to consider and make finite capacity for production or transportation , it's working fine no problem but when you run PP/DS he not respect all what you did in SNP

what's the propose from doing all this in snp optimizer ??

Please I need clarification for this concept

Regards

Rami