on 02-22-2013 2:08 PM
HI ,
My issue is :
i have created PO and able to see print preview. in SPRO I have set adobe form ( zpo_adb )for application BBP_PD and for application BBP_PD_PO and in process type .
This form is triggere when i order PO. It works fine...........
But. when i changed po...and triggered output ...then BBP_PO smart form is called. I am not aware how come this std form is called instead of
adobe form zpo_adb i configured in SPRO.
Please do needful.
Regards
Ramakrishnaiah
HI,
this scenario is in SRM.
RegardsR
Ram..