on 02-27-2007 4:02 AM
Hi
I have created the order form my material with quantity of 10 units. The total unrestricted stock available for the material is only 5 units.
When I look at the schedule lines, the total order qty is confirmed even though the short of 5 unit of stock.
I was confused here. By right, the order should only confirm the 5 unit with respect the stock availability. But I dont understand why system has
Confirmed the 10 units completely.
If my understanding is correct, the sales order has to confirm the sales order based on the stock. In later stage, once the stock is up, we need create the
Schedule line for the remaining qty by re-do the availability check function.
Could you please someone correct me on this order confirmation logic !!
Regards
Priyan
hi
Check which type of availability check u have entered in the AC Field. If it is No Check system will not consider AC
Regards
MBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shankar Mani MBS
Thanks for your replies.
Could you please advice anything wrong with below material setup?
AC = 01 Daily Requirements
MRP Type = ND
Procurement Type = X
Total RLT = 0 Days
In-house Production = 0 Days
GR Processing Time = 0 Days
Planned Delivery Time = 0 Days
Strategy Group = Blank
Regards
Priyan
Hi SS
Order is a normal (Type: OR) Trade order. And there is no consignment stock maintained for this material.
In MMBE, I can see only unrestricted stock exist for this material.
Please confirm whether my material setup is correct.
It is usual vanilla setup.
My doubt is that how come the order item has been confirmed with excess qty and system allows us to create the delivery as well.
Firstly, on what basis the order full qty has confirmed.
Please advice.
Regards
Priyan
Hi,
Did you test your set up with any other material? Most likely you are missing to notice some PO's in the system or some material receipt pending verification. Thats the only to explain the scenario.
May be you can verify OVZ2 t.code and see if there is any AC happening during dely creation. If this setting is blank, then the system will not check for the actual qty for creating the dely.
Hope, this explains.
S. Siva
Hi Siva
Thanks for you to help me to check the setup OVZ2.
01 - Daily requirements is been specified in OVZ2 as follows
Total Sales = B (Totals Records per Day)
TotDlvReqs = B (Totals Records per Day)
Block QtRq = Marked
No Check = NOT Marked
Accuml. = Blank
Response = Blank
RelChkPlan = Blank
It seems nothing wrong in this setup.
Another material (same MM setup) is also the same problem
But one thing sure in my case like, the AC has not carried out due to some reason.
Regards
Priyan
Hi Priyan;
Pls check if you have an open Purchase Order for this material, this could have been taken into accountwhen the availabilty check was done.
Also another possiblity is that RLT which we would have maintained in the Material Master.
Pls check the same and what settings are there.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There might be RLT check was ticked in your scope of avblty check and also check the replinishement lead time mentioned in your material master. If RLT is ticked system will confirm the stock.
Cio Shankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.