Alternative date validity in BOM

Former Member
0 Kudos

BOM is having 7 Materials in it. Header is valid from date set in change number say today 21/02/2013. if I want to set validity date for the child components say for first 3 materials I want to set validity date as 25/02/2013,

next 2 Materials validity date as 27/02/2013 and

last 2 materials date as 01/03/2013. is it possible ? if so how? please share if documents or links reg this

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Component validity date can't be defined by user.

It is coming based on the change date on which the particular component has been added.

If first 3 components are added on 25/02/2013, then it will have validity date of that. If another 2 components are added on 28/02/2013, then it will have validity date according to that.