Realignment and life cycle planing process-apo dp

Former Member
0 Kudos

Dear APO experts,

I want know the simple detail explanation about these two process in APO DP.Please explain with examples.....it would be understand easily.

And what is the difference of these two plannings?under which scenario are using?

Please don't take embarrass to explain.

Expecting healthy need information.

Thanks&Regards

Chowdary

Accepted Solutions (1)

Accepted Solutions (1)

emani_raghavendra
Participant
0 Kudos

Dear Chowdary

Life Cycle planning is used for forecasting new products. Realignment is used to transfer the demand of an existing SKU to another existing SKU.

Scenario's :

> When a company lauches new product in the market , then that product doesn't have any history . For Forecasting any product we need history data . The company needs to calculate the demad of this new product in order to meet the requirements. For this kind of scenario , Life cycle planning is used.

In Life cycle planning , they take some reference Product which is a bit similiar to the newly lauched product and copy the history on percentage basis of the existing product to the new product and then they calculate the demand for the new product. This gives them a rough idea about the newq product which was lauched recently. here we should remeber that the newly lauched product will not capture the market on immediate effect. it has a slow growth in the market with different phases, like launch phase, growth phase, et.c. So we copy the history of the existing product on percentage basis.

> Realignment is used when there is some change in the structure of a product / customer area and also when we want o transfer the demand from one product / customer to other product / customer.

Suppose, currently a product " Milk " is under a product group " Liquid " . Now, the businees want to change to change the product group from " Liquid " to " LIQUID10LIT " , then we should realign the product group of the product " MILK ". That means, all the history and the demand of product " MILK " will now be transfeered from product group " LIQUID " to " LIQUID10LIT ".

Also, if some Product has become defunct and i want to transfer its demand to another product which is existing in the market , then also we can use Realignment

In simple terms >>

>>>> Life Cycle Planning , is a techinique  to calculate the forecast of newly Created Products.

>>>> Realignment is just transfer of estimates from one product to another product. here forecats is not getting calculated . only transfer happens.

For any further queries , pls revert.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello ,

In simple words when you only want to use the the history or sales data of an old item to plan for a new or a similar item you will use Re-alignment.The new item need not substiture the old one.

But when you want to substitute an old item via a new item you will you will use Life cycle planning. In this New item slowly captures the market and old item slowly phases out from the market.

Hope this gives you a hint.

Regards,

Anurag

Former Member
0 Kudos

Dear all,

I am very thankful to these persons such a quick response and especially raghavendra explanation.

Thank you for spending time...

Regards

Chowdary

Former Member
0 Kudos

Hello Chowdary,

Good to know that it helped you.

Could you please also mark the thread accordingly.

Regards,

Anurag

prmandavia
Explorer
0 Kudos

Hello Experts,

Need to know one thing - if we need to Transport Lifecycle Planning settings from development to production through QA. I am not sure how we can capture lifecycle settings in a transport.

Also the same question for realignment settings.

Please advice. Appreciate the help.

Regards,

Prakash

Former Member
0 Kudos

Hi,

Basic settings for Lifecycle Planning Settings are not transportable.

These can be setup using transaction '/SAPAPO/MSDP_FCST1' on the production system.

It's recommended access to the basic settings is locked down for end users.

Regards,

Ali