cancel
Showing results for 
Search instead for 
Did you mean: 

ChaRM dual stack setup - Transport domain clarification

Former Member
0 Kudos

Hi Expert,

currently i am working on PI Landscape ChaRM configuration .

Scenario:

ABAP stack - transport domain is Development system and create the transport link between solman and ABAP system.

Java standalone system - transport domain is solman system then

DEPLOY_WEB_SERVICE:            CTSDEPLOY

COMMUNICATION_SYSTEM:     <solman system id>

NON_ABAP_WBO_CLIENT : <client>

for Dual stack system( PI Landscape) - which system i need to transport domain system( solman or PI dev system)

currently i have configured transport route in PI ABAP development system.but non-ABAP setting in SMSY missing

Also system details is missing in  database table SMSY_SYSTEM_OTO.

Could please help to fix it.

Rg,

Karthik

Accepted Solutions (1)

Accepted Solutions (1)

shyam_dontamsetty
Active Participant
0 Kudos

hi karthik,

For charm specific case,make your solman(ABAP) as your transport domain and connect your PI (ABAP+JAVA) and stand alone JAVA to transport domain.

Standalone java details missing- check host agent is running? or not.

Best Regards,

Shyam

Former Member
0 Kudos

Hi Shyam,

I am using PI Dev landscape is transport domain for both ABAP and JAVA. configuration the relevant CTS+ parameters. once i assigned logical component and created the project and after chaRM activation, during the check i am getting below issue

Above issue clear say "No consolidation system" found. i am using ABAP transport route only.ABAP setup is working fine. whether i need maintain any settings for java stack?

Also i am using SAP Solution manager 7.1 SP04 version.

Also i refered dolores sdn link,

http://scn.sap.com/people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-qu...

"

In Solman 7.1 this issue will be solved by using the long SID functionality provided by SMSY, that is, systems in different transport domains with the same SID can be managed by charm"

In my landscape both ABAP and Java having same SID, whether i need to change the java Extended system sid in LMDB?

Please give some help to setup ChaRM for dual stack system.

Rg,

Karthik

shyam_dontamsetty
Active Participant
0 Kudos

hi Karthik,

Check this SAP note:Note 1573825 - ChaRM: only use ABAP stack for a dual stack system

Best Regards,

Shyam

Former Member
0 Kudos

Hi shyam,

It is not relevant to my requirement.

"After implementing note 1573825, you will be able to define such systems as pure ABAP stack system, so no CTS+ configuration is needed for them."

But my case is i need CTS+ configuration in dual stack.

Rg,

Karthik

shyam_dontamsetty
Active Participant
0 Kudos

Hi Karthik,

Please go through this doc and check if all the configurations are done .

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/20ccd0ec-2839-2b10-0097-828fcd8ed...

Best Regards,

Shyam

Former Member
0 Kudos

Hi Shyam,

I have maintained all setting . i found missing entry for a technical system of the type in the table SMSY_SYSTEM_OTO.

Some issue in stms synchronization between PI and Solman . i am checking on it.

Rg,

Karthik

Answers (1)

Answers (1)

markus_zoller
Discoverer
0 Kudos

Hi Karthik

I had the same problem.

Look at the note  1999716 and 1787917  🙂

Rg, Markus