Dear Sirs,
I'm trying to assign work orders for Material PRT. I know that equipment PRT can be used in a Maintenance Item of a Plan, but how can I do if I want to mantain with work orders a Material PRT, I have the material PRT created, but what configuration or how can relate work orders in order to maintain a Material PRT.
I hope your repplies, thanks.
Check the process of Refurbishment. This process is useful for the maintenance of Repairable Spares.
So its possible to map that process for Material PRT as well.
Also this query is related to Enterprise Asset Management Forum. Please use right forum for your queries.