I found that Plan integration includes the following functions:Revaluation of planning objects following price changes.When a CO activity price changes, the integrated planning objects are automatically revalueed at the new price.
But I am not sure how to revaluation the cost of he Integrated wbs.
I had created a wbs with the "Plan integration" indicator in the project profile.And I set the "Plan integration" indicator in the detailed view "Settings per fiscal year" for the plan version. Then I assigned a internal activity to the wbs and saved the wbs, the plan cost of the activity =Work*price( Activity Type). Then I changed the price of the Activity Type, but the activity plan cost which I checked with the cost report did not changed.
I dot know whether my scenario is right.
Can you give me a example or a scenario? thank you!
Hi Jian Mao
This indicator specifies whether an order/project participates in integrated planning or not. You define this per project profile for projects in Customizing:
For orders, you can store a default value in the order type, which you can change in the order master data when required.
Activity inputs planned in a plan-integrated order/project are updated directly on the sending cost center if 'Integrated planning with Cost Center Accounting' is activated in the version. You can then also settle plan-integrated orders/projects to cost centers.
Plan data is passed on to the profit center and the extended general ledger if both 'Integrated planning with Cost Center Accounting' and the "Integrated planning" indicator are activated in the version.
Changing the "Integrated Planning" indicator
You can change the "Integrated planning" indicator at a later date under the following conditions:
Hope this would give you more understanding about Integrated Planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can anyone explain for me what is the integrated planning on wbs? It is better to make a example.thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
'Plan integration' on WBS means that any activities planned for WBS element(in CJR2 planned hours for an activity or networks) will update the information in sender cost center.
If you know, cost center planning where all the planned activity units or cost are manually planned.
If you this indicator on WBS, all the activities planned on WBS will also reflect in cost center planning.
For more information, you can discuss this with CO consultant from your team.
Regards,
Mahendra
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.