on 02-19-2013 1:00 PM
Hi ,
Scenario :
if any material is not having all the master data on ECC side even then APO allows the conversion of SNP planned orders to PPDS planned orders and the error is reflected in CCR transaction as not in R/3.
But if stuck for long it gave PPDS planned internal order no as 000000000 on conversion which was then accidentally converted to production order and the planned order could not be traced back .
I want to restrict the conversion of SNP planned order( AJ) to PPDS planned order (AI) on conditional basis so that this scenario is not recreated.Condition being a check for all master data.
I would be good if suggested with a standerd solution rather than development
Hi Mohita,
Please check SAP note no. 481906 for information on SNP to PPDS conversion, it might help you.
For further info on this, please check SAP help.
http://help.sap.com/saphelp_scm70/helpdata/EN/c5/c4703736bfb37de10000009b38f8cf/content.htm
Rgds
Sourabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.