on 02-19-2013 7:18 AM
Dear PS experts,
Could anyone please let me know from which table i can get the Project Budget Assigned Values?
I can get the current budget and supplements from RPSCO but unable to find the assigned values
Your early reply is greatly appreciated
Regards
Srinivasa
Hello,
You can have it in table BPGE,
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Srinivasa,
You can find Budget values in table RPSCO as follows.
1) Budget - Value type 41
2) Actual- Value type 4 & 11
3) Commitment- Value type 21,22,23,24 & 26
4) Assigned- Formula: ActualCommitmentRemOrdPlan (RemOrdPlan- Value type 25)
5) Available- Formula: Budget-Assigned
Also refer Budget tables in database at
http://help.sap.com/saphelp_erp60_sp/helpdata/en/c3/2c344071c82b22e10000000a1550b0/content.htm
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.