SAP table for Project Budget Assigned Values

Former Member
0 Kudos

Dear PS experts,

Could anyone please let me know from which table i can get the Project Budget Assigned Values?

I can get the current budget and supplements from RPSCO but unable to find the assigned values

Your early reply is greatly appreciated

Regards

Srinivasa

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member209919
Active Contributor
0 Kudos

Hello,

You can have it in table BPGE,

Regards

Former Member
0 Kudos

Hello Srinivasa,

You can find Budget values in table RPSCO as follows.

1) Budget - Value type 41

2) Actual- Value type 4 & 11

3) Commitment- Value type 21,22,23,24 & 26

4) Assigned- Formula: ActualCommitmentRemOrdPlan (RemOrdPlan- Value type 25)

5) Available- Formula: Budget-Assigned

Also refer Budget tables in database at

http://help.sap.com/saphelp_erp60_sp/helpdata/en/c3/2c344071c82b22e10000000a1550b0/content.htm

Regards

Tushar