on 02-15-2013 12:32 PM
Dear All,
I have activated negative stock for the below
Plant
ST.location
Special stock.
thought not needed at material type also.
Now I have created a SO and trying to deliver but system is saying no schedule lines. As i'm trying this in a test system I have put some stock for the respective material and sales order and tried to create delivery docuement then it got created.
The schedule lines have been confirmed.
Please let me know is there any setting I have missed?
Regards
Manish
Hi,
You need to maintain the negative stock check box in Material Master also.
I am not having access to SAP, but I think it is in MRP view.
Regards,
Amitesh Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
What is business process behind this requirement? For negative stock I think you mean there is no stock and you want system to allow pgi. If there is no stock how system can confirm schedule line for this. Please correct me if I am wrong.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.