Dears,

When I run SNP optimizer in background and put the production capacity and transportation capacity as constraint

I have only two demand  from DC 2014 to PP 2013

I found 25 SNP -Planned order created after optimization finished

Why it's not restricted only to Demand Quantity

Your Help Highly Appreciated

BR,

Rami

Accepted Solutions (1)

Accepted Solutions (1)

rajkj
Active Contributor
0 Kudos

Hi Rami,

Have you defined max lot size for your location product? If so, delete the value so that one planned order will be generated.

Thanks,
Rajesh

former_member182449
Participant
0 Kudos

Hi Rajesh,

No , I have not defined max lot size in location product .

Please Advise

Rami

former_member182449
Participant
0 Kudos

Dears,

The cost of PPM was blank

You have to maintain cost in PPM

Issue Closed

BR,

Rami