When I run SNP optimizer in background and put the production capacity and transportation capacity as constraint
I have only two demand from DC 2014 to PP 2013
I found 25 SNP -Planned order created after optimization finished
Why it's not restricted only to Demand Quantity
Your Help Highly Appreciated
BR,
Rami
Hi Rami,
Have you defined max lot size for your location product? If so, delete the value so that one planned order will be generated.
Thanks,
Rajesh