Hi SAP gurus,

I am facing what seems to be a recurring problem: I want to CIF Sales BOMs (BOMs with usage = 5) from ECC to APO, but the resulting PDSs only have the header with no components.

If I CIF BOM of other usages (for instance 1) then they result in perfectly complete PDSs with header + components.

We are under ECC 610 and SCM7.

I checked that all components and headers are in active material IMs, and BOMs are active and selected in the BOMs IMs.

this was already discussed in several SCN threads with no answer:

http://scn.sap.com/thread/1480978

http://scn.sap.com/thread/1472379

Do you know how to get the CIF to send these BOMs?

thanks a lot for your help!

Hugues

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Hugues,

Make sure your BOM components are production relevant.

CS02 -> Double-click on item number -> Select "Status/Long Text" -> Check Production Relevant flag.

Repeat for your other BOM components.

Best Regards,

Mike

Former Member
0 Kudos

Thanks Mike,

it worked perfectly.

I’ll have to dig into whether this could have side effects though.

would you know any other (standard) way to make this work ithout changing the production relevancy? (which is actually dependent on the BOM usage - so it’s like I created an hybrid production-sales BOM)