on 02-13-2013 7:51 AM
Hi Experts,
I am facing a new error while performing a regular activity in SAP APO PP/DS module.
Our regular activities include 1) Creating Material Variants
2) Uploading BOM file through a 'z' developed transaction in iPPE
3) Ciff the data from R/3 to APO
4) PDS (to attach BOM to Material Variant)
5) Planning Run (to generate Planned Orders)
6) RPMCALL (to attach BOM to Planned Orders)
Now while taking a RPMCALL, it gets cancelled stating "An error has caused the RPM run to be canceled" and when I checked the RPMLOG the error is "Row keys for tokens used up".
I am trying to fix this error, but not able to do so. Kindly help me out.
Regards,
Abhishek Somshetti
Issue resolved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.