plan cost not updating

Former Member
0 Kudos

Hi Expert,

I plan cost in cj40 with version "0" but it's not coming in report cns41 i set the layout with field (Proj.cost sched.000) what is the reason please help me out.

Regards,

Aryan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Aryan,

Go to OPSB and check your planning profile. Check if there is tik mark for Planning elements under Manual planning.This indicator controls whether cost planning is possible only in those WBS elements which were defined as planning elements.

Regards

Tushar

Former Member
0 Kudos

Thanks for replying Tushar,

how to save selected fields layout in cns41 report?

Regards,

Aryan

Former Member
0 Kudos

Hi Aryan,

You can save selected fields layout in CNS41 report as Selection version

Once you select specific fields , directly save the report as specific selection version by entering some description ( For e.g Test-Project etc)

Regards

Tushar

Former Member
0 Kudos

but once again i open report cns41 with concern project and execute selected field doesnot come.

Regards,

Aryan

Former Member
0 Kudos

When you execute CNS41 report, go to DB profile and click on Version data.

This will enable field Version data. You can enter name of the version you have saved earlier and tik mark on Version data.

Now try executing the report. It should give you out put with selected fields.

Regards

Tushar

Former Member
0 Kudos

Hi Tushar,

Still same problem, is there any other reason for not updating plan cost in cns41 report??

Regards,

Aryan

Former Member
0 Kudos

Hi Aryan,

If you have done config changes, try once Reconstructing Project info database through CJEN.Then observe CNS41 report.

Regards

Tushar

Former Member
0 Kudos

Hi Tushar,

i think i have complete config for plan updating as

order appended cost planing

planing profile check mark with manual

in network structure network type planning as tick mark also

is there any other point wherein we need to check please suggest??

I have alredy done cjen after changing in config then execute cns41 but still same problem.

Regards,

Sanjeev

Former Member
0 Kudos

Hi,

Go to OPUV for combination of Plant and Network type.

Check indicator for Plan.Cost Calc.It should be Determine Plan costs.

Regards

Tushar

Former Member
0 Kudos

hii

i think u have to do some customize in back groud of user status to allow plan line items

Regards

Sunil Kumar M

Former Member
0 Kudos

yes determine plan cost is there in OPUV

Former Member
0 Kudos

below business transaction is in allow mode and authorization code ZPS0000 is there what should i do now ???

Write budget line items     allow

Write plan line items          allow

Former Member
0 Kudos

Please refer to SAP Note 148971 - Planned values in Project Information System

Also refer to discussions in below mentioned threads

http://scn.sap.com/thread/2097350

http://scn.sap.com/thread/1168856

Regards

Tushar

Former Member
0 Kudos

Hi Tushar,

system say can not impletemented Note 148971. next what is the solution??

Regards,

Aryan

Former Member
0 Kudos

Hi Aryan,

If your system say that it can not implement SAP Note 148971, then I would suggest you to raise OSS message to SAP.

Regards

Tushar

Answers (4)

Answers (4)

Former Member
0 Kudos

hii

i think u have to do some customize in back groud of user status to allow plan line items

Regards

Sunil Kumar M

Former Member
0 Kudos

Hi Aryan Kumar

Please go to IMG network type, in the Control Indicator Tick Mark Planning

Hope this may solve your issue

Former Member
0 Kudos

Hi Aryan

Please Check this report 12KST1E Costs: Plan/actual/down pymt as expense

check if the plan cost are updating in this report

Former Member
0 Kudos

Hi Vijay,

plan is updating in more another report as s_alr_870...... and CJE0 with 12KST1E as you suggest but requirement is in structure report as cns41 cn41 cn41n and more.

Regards,

Aryan

Former Member
0 Kudos

Hi Aryan

T code CNS41 initial screen, Select the DB Profile Tab , Tick Mark  Planned Orders and Expenses

This  will show planned cost in report.

Please rever back if any issues

Former Member
0 Kudos

Hi Vijay,

thanks for your reply but already tick mark in miscellaneous objects as you suggest planned ord and expenses.

Regards,

Aryan