“CO planned data interface line entry”.

Former Member
0 Kudos

Good Evening PS gurus,

I observed in CJI4 there is amount 2000 USD under document header text column as “CO planned data interface line entry”. I would like to know through which transaction these entry was made.  (integrated planning is not activated in this scenario)

Note:

Amount which was planned through CJR2 has Manual Planning Release 731 under document header text in CJI4.

Please help

Praveen Y

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member209919
Active Contributor
0 Kudos

Hello Praveen,

I think this posting it is not standard, if not it have been developed in your system. You can check at what time was created and the user, if it is a general user ( like a BATCH user) this has been created by a program/ idoc, check if you have any idoc at this time .

Regards

Former Member
0 Kudos

Thanks Sara,

But i am getting the clear user sap ID. Which means that entry didn’t happen through backgrond Job.

Mostly all entries in document header text column as “CO planned data interface” happened through one date with minor difference in time.

Regards

Praveen Y