on 02-07-2013 5:44 AM
Dear Experts,
In report S_ALR_87013558 we can see all details but I found confussion in Actul Cost,when I want to see the line items ( with header and with T.code CJID also) it show the wrong figure.How or with another detials t.code I can compare the accurate value of Acutal Cost with this reort?
Please help
Regards,
Rajesh Chauhan
Hi,
Check in CN41N report which gives output withput filtering etc.
Also run CJEN for this project and recheck.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the report CJI3. Filter the report for value type 4. This should give you the actual cost for the entire project. Compare this later with whichever report you feel like. You can also try the standard hierarchy report S_ALR_87013531. This report will also show you the actual cost according to your project structure.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rajesh,
In addition to above inputs, kindly verify actual cost in standard report like S_ALR_87013542.
Report S_ALR_87013558 only shows the project actual cost whereas CJI3 and other reports (For e.g. S_ALR_87013542) also include the settled cost as well.
We are also facing little similar issue in our project. When we raised OSS message on this issue,SAP replied that CJI3 reports fetches the details from both active and archived tables and where as when we drill down from budget reports to line item reports system reads the data from active tables only. And the fix is to implement SAP Note: 1136779.
Check if this note is relevant for your case.
Also go through discussion on below thread
http://scn.sap.com/thread/2025725
Regards
Tushar
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.