Projects missing when building BPH

Former Member
0 Kudos

Hi All,

I'm having an issue where 2 of my projects defined in SOLAR_PROJECT_ADMIN are not showing up when I try to build my business process hierarchy in SOLAR01.

I'm changing the source to Project:

When I then try to select my project, the one I want isn't listed. I see 11 other projects, but 2 are missing. The 11 projects are a mix of template projects, implementation projects and maintenance projects. The 2 projects missing are template projects.

All projects have the status Open. None of the projects have their structures locked on the Scope tab.

Has anyone see this before? Any ideas how I could troubleshoot this?

thanks,

Jason

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Jason,

    

the project selection within Solar01 lists only those template projects that have no
template assigned in project administration (Solar_Project_Admin). The reason
is that it is expected that content from template projects with template
assignments is taken over via the scope tab in project administration and not
via selection help in Solar01.

   

Best
regards,

Michael