WBS is locked due to system status BMLK is active

former_member330379
Participant
0 Kudos

Dear Experts

Due to system status BKLK is active for WBS , we are not able to assign supplimentry budget

following error are coming :

System status BMLK is active (WBS NP-A075-0001-0001)

Message no. BS013

Diagnosis

Object WBS NP-A075-0001-0001 has system status BMLK (Budget management locked).  According to this status, transaction 'Budgeting' is not allowed.

Procedure

You can only carry out the requested function if this is allowed according to the status of the object.

Please suggest

Regards

shailesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member195427
Active Contributor
0 Kudos

Hi

    You need to unlock the system status BMLK for WBS in PB.

Select  WBS NP-A075-0001-0001  >Edit>Status>Unlock>Budget.

Regards

Ankur

former_member330379
Participant
0 Kudos

Dear Ankur ,

It's being resolved already with the same process which you mention.

Thanks a lot

Regards

shailesh