on 02-02-2013 6:08 AM
Hi,
Is it possible to change inspection specifications in results recording. Or if I change it in quality plan does it change in the lot after it is released |
Regards
Badri
Is it possible to change inspection specifications in results recording.
- NO ,Not possible.Once Inspection plan is assigned & sample is determine ,you can not change specification.
if I change it in quality plan does it change in the lot after it is released
-Every change in Inspection plan will reflect in IL after creation of new inspection lot.