on 02-02-2013 4:54 AM
dear all
my process is MTO process
when create the order the it trigger GATP , here order quantity will conform ,
then create the delivery here delivery quantity comes automatically , because delivery level also trigger GATP ,
but process MTO order , when create the order then delivery here delivery quantity comes zero , because r/3 atp checking control level you activate the with out RLT , Then you assign the quantity at MB1B 412 E movement , then it create the delivery now comes the allocation quantity , with same behavior i want
Delivery GATP also , pl advise
r/3 atp control screen
pl check screen and advice
regards
sankar
hi all
any body give the response pl i am waiting its need full
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bojja,
In a pure MTO scenario, you want to trigger your production as and when you recieve sales order, and based on that your order will be confirmed.
From the copy control between sales order and delivery document, you determine how the data will get copied from sales order to delivery document.
So, if your order is fully or partially confirmed and you are creating delivery document from sales order, then confirmed quantity from the schedule line will get copied into delivery document.
I have not heard of any scenario where you don't want quantity to be copied from sales document to delivery document.
What exactly you want to achieve with zero quantity in delivery document, if you can share exact requirement which is leading to this, will help in further understanding.
Rgds
Sourabh
Hi,
Are you first of all clear, what you want to achieve,
"i am creating the order va01- this order is MTO , then make a delivery here delivery quantity comes sale order quantity , but MTO process when you create the order the then delivery here delivery quantity comes zero ,
i need delivery quantity is zero"
You said you want to have delivery document with quantity '0', which shouldn't be the case unless you have very valid point for supporting this requirement, and there is nothing you can do for this in APO.
All you will have to do is check your copy control settings only.
APO GATP have functions like CTP / MATP to support MTO processes.
But, nothing works beyond availability check.
So, here you need to be sure of your requirement.
Rgds
Sourabh
User | Count |
---|---|