We want to change some logic to the forecast consumption in APO; in more detail, we want to change it whenever a new order is sent over from R/3 to APO.

The goal at the moment is to have the consumption done based on the confirmed delivery date (which is used for GATP).

Integration is working, consumption is working, only the month is somethimes not ok.

A prerequisite is that we should not touch the order in R/3.

Can somebody indicate in which bapi, Function module, badi, .... the forecast consumption is happening in APO? ARe there some user exist that we can use to influence this?

are there already some persons who did this?

regards,

Tommy

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Tommy,

Can you please elaborate.  Are you talking about SNP?  PP/DS? or.....?

Best Regards,

DB49

Former Member
0 Kudos

Hi,

this is forecast consumption in the SNP planning books. But it is also visibile in the forecast tab of the product view.

Regards,

Tommy