Hi Experts,
Please share your thoughts on the below :
1. How does SNP deals with Non production weeks at the factory in a given horizon? Please share the configuration settings..
Please note we will not be implementing capacity leveling and PPDS here.
Thanks for your response and appreciate your inputs.
NLN.
Hi NLN,
Typically, SNP uses calendars (t.code /sapapo/calendar) that are assigned to location master (t.code /sapapo/loc3 - calendar tab), t.lane, and resource to enforce the working hours/day and non-working days.
The calendar i.e. time stream transaction allows you to define periods in a flexible way. Then, macros access these calendars to determine the working days. Pl check standard SNP macro "Determine work days" in the macro builder for details.
Thanks,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.