Hey guys,
could anybody give advice on how to upload an excel file to create an initial Business Blueprint Structure in SOLAR01. None of the already posted threads and relpies on this matter are really helpful.
Thank you very much.
Hi Martin,
In solar_project_admin, after accessing the project, access the option:
Edit -> Fill business blueprint->create template file -> structure
All options under "create template file" will generate a file for download that you should use as reference on how to fill the information and then afterwards you should use the option:
Edit -> Fill business blueprint-> Upload file -> ...
to use the file you created as reference to fill the project data.
The file generated in the first option will have examples and the possible type of data to fill.
kind regards, Fabricius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I checked the same. But when you would like to add additional nodes, you may not have the node ID. How do you manage to upload the excel file without node id? Pls refer to
SAP note # 1641864 - FAQ:
Business Blueprint Upload functionality
The structure creation works only for new projects.
Hi Martin,
Process is simple
transaction is only one SOLAR_PROJECT_ADMIN---------------Standard SAP menu option.
If you are looking for screenshots and more details check my article here
hope it clarifies and help you achieve the same
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.