Hai,

Small question. Can we have a planning area initialized for more than one version at the same time?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

yeah you can have more than one version initialized at the same time

and it is quite common in DP particularly if you want to use different versions for simulations and to keep data from different groups separate or to copy from one version to another to manipulate data

SNP/ PPDS is a slightly different.

Firstly, though you can have different versions for simulation, 000 is the active version

a lot of masterdata that is used in SNP/PPDS is version dependant too

there are also a few details about the Planning version setting that can used in interactive planning (such as time zone)

Answers (1)

Answers (1)

somnath_manna
Active Contributor
0 Kudos

Of course.

Multiple planning versions with different horizons is very much possible.

Somnath