on 01-30-2013 5:55 PM
Hi ,
We implemented subcontracting scenario (without work order collaboration)in SNC. Now customer wants to see how much component supplier is consumed in ECC.
Example
I sent Subcontracting PO for assembly for qty 10 to SNC which consists of 2 components.
Now supplier used extra 2 component to manufacture assembly.i.e 12 Each
Supplier confirmed PO of 10 numbers with 12 components each. When I see the xml it consists of component information. But when idoc gets created in ECC there is no component information. Even after sending ASN we were not able to see any component information in ECC.
Note:
We are not using approval process in PO collaboration.when supplier confirms the PO it is generating ROC_OUT in SNC.In ECC it is generating ORDRSP of type ORDERS05.
Regards
Raghavendra Pai
You are using wrong Idoc -ORDERS05, you should be using PORDCR1, or better yet switch to XMLs
J.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raghavendra
If you can upload some data we can try to do some analysis
Regards
Anindya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.