on 01-30-2013 12:48 PM
Hi,
We are using SCM5.0 and SAP ECC 6.0.
We try to change source of supply in APO e.g. from PDS14 to PDS15 for process order.
PDS14 - having line2
PDS15 having line 3
After change in APO we could see Line3 appears successfully in APO but when we go to ECC and check details of process order
I could see PV14 is replace with PV15 but when I check " Process order material list " only for one material ( semifinish item) storage location is not changed.
but when we do it in ECC then could see change in storage location for that material ( semifinish item) happens successfully.
please suggest
Regards
Samir
Dear,
Could you please check the sub location defined in your PDS? Is it updated one. Also check storage location defined in your production version.
Please re CIF the PDS to APO and then try the same.
Did you get any error in CCR run?
Please note system uses the default issuing storage location maintained in the production version of the master output component. If there is no default issuing storage location maintained, the system uses the receiving storage location maintained in the production version of the master output component
Please refer OSS Note 1651967 - INT-PDS: Storage location determntn not supported
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.