Hi

SD gurs

if in house  production time (MRP) AND RLT are used simulationly which one  does the system give priority to?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member620323
Active Contributor
0 Kudos

Hi,

In house  production time Specifies the time in workdays needed to produce the material in-house.

Means Production time.