Hello Experts,
We are working on RLM scenario where the material is stocked at both Offshore & Base locations.
We are facing an issue.. When there is no stock at at the offshore location and MRP run (at Offshore) triggers a Purchase / transport requisition as expected.
How does this TR gets converted to Transport Order. Documentation says there is a conversion program. Does it require any config to activate it.
Regards,
Venkatesh
06-01-2015 11:48 AM
RLM Supply Process Configuration for "Supply Types" and "Supply Process Derivation" should be set to STR and STO for Stock Offshore and Onshore.
Tx: O3O_SC01 can be run (in batch) to auto-create associated STOs.
06-01-2015 11:48 AM
RLM Supply Process Configuration for "Supply Types" and "Supply Process Derivation" should be set to STR and STO for Stock Offshore and Onshore.
Tx: O3O_SC01 can be run (in batch) to auto-create associated STOs.