Hello Everybody
Hope all are doing well. I wanted to know the procedure to load Calendars from ECC to APO.
Regards
Rachel
Hi Rachel,
Follow below steps for transferring factory calanders from ECC to APO.
1) Go to Transaction RSA1 in APO
2) Select Source systems ------> SAP ------> your R/3 client -----> Right click on the client
-------> Select Transfer Global Settings ------> Select Factory Calendars ------> Select Rebuild tables.
You will be able to transfer factory calanders from ECC to APO with these steps.
Do let me know in case of any query in this.
Rgds
Sourabh