How do we load the Calendars to APO from ECC

Former Member
0 Kudos

Hello Everybody

Hope all are doing well. I wanted to know the procedure to load Calendars from ECC to APO.

Regards

Rachel

Accepted Solutions (1)

Accepted Solutions (1)

sourabh_jain66
Active Contributor
0 Kudos

Hi Rachel,

Follow below steps for transferring factory calanders from ECC to APO.

1)  Go to Transaction RSA1 in APO

2) Select Source systems   ------>  SAP  ------>    your R/3 client      ----->   Right click on the client

------->     Select Transfer Global Settings   ------>   Select Factory Calendars    ------>   Select Rebuild tables.

You will be able to transfer factory calanders from ECC to APO with these steps.

Do let me know in case of any query in this.

Rgds

Sourabh

sourabh_jain66
Active Contributor
0 Kudos

Hi Rachel,

Is this answers your query, if yes please close the discussion.

Regards

Sourabh

Former Member
0 Kudos

Thanks Sourabh