on 01-28-2013 4:04 AM
Can I have two settlement rules for a WBS in a project?
One should trigger after other .The First settlement rule for WBS would settle it to a cost center and the next settlement rule would settle to another Final WBS(project) after the first project is closed.
Thanks!
Hi,
You can have multiple settlement rules and that is not an issue.
However you have to define percentage of distribution for each rule and maintained distribution rule numbers.
In your case, you can set the period from to period to (dates in CTR) in those two columns so that basing on the end date (period to) being maintained the settlement receivers, sysmte will not settle costs further more.
Thanks,
Sudhakar
Message was edited by: Sudhakar Pappu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
first let me know why you want settle cost to another reciever object while you have settle cost to CC??
Regards,
sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.