cancel
Showing results for 
Search instead for 
Did you mean: 

RE: Units of different dimensions cannot be converted

Former Member
0 Kudos

hi

i got error in sap ps cn41n

Units of different dimensions cannot be converted

and i cheking in cj20n under network no material components. Plz. provide solution

 

thks

apr

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Prasad,

Please check if there was any change of unit has been done in activities after partial confirmation has been done. When confirmation has been done in new unit, this error can come.

You can try not to confirm this activity and delete that activity. Subsequently save the network and attach new activity again and then can confirm activity.

Try this scenario in test system and check if you are still facing same error.

Regards

Tushar

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Can you let me know  what you are doing in CN41N so generated error.

Regards,

Sudhakar

Former Member
0 Kudos

hi ,

cj20n level deleted material component  and activity and unconfirmed the network then deleted the operation system not allowed.

pl see below i run report cn41n

kindly help me

thk&rd

prasad

MohanDesai
Active Participant
0 Kudos

Hi Prasad,

Already Tushar has given some points. If you can share the screen shot of your Activities created it can be useful in resolving this issue.

Regards,

MRD

Former Member
0 Kudos

Hi,

i checking prod server wbs element releated PR 'S

1.all PR released

2. PO released> migo > miro> material doc transactions completed

i created under wbs element new n/w>activity> material component>network released > save

same error getting

kindly suggest me process

>cn41n

Former Member
0 Kudos

Hi,

With your posting absolutely cluelss and does not make sense. Sorry about that.

Go back to CJ20N and create a new network activity and check for default UoM and compare with other activities which are already in the project. If you notice mismatch please change it.

Then go to tac-OPUU (Maintain network profiles) on the tab Activities check what UoM was maintained there. Hope you must be using internal activity with control key PS01 (ZS01) whatever you might have done customization.

Message was edited by: Sudhakar Pappu

Former Member
0 Kudos

Hi,

opuu

internal activity

activity tab under we are maintain below see

control key ps01

unit for work= day

normal dur unit =day

cal key =2(cal.work

service activity

control key=ps04

cost element=45252

m.group=service

uom=au

kindly suggest me if config required i am asking one question

why it is getting error in cn41n report

Units of different dimensions cannot be converted

ts error only one project remaining all project working fine cn41n

thks& rds

prasad

Former Member
0 Kudos

Hi,

Go back to PB and check what was default UoM in that particular activity. Other than "day" delete manually and input "day".

Create another activity and check for default UoM.

Regards,

Sudhakar

Former Member
0 Kudos

Hi,

i Create another activity and check for default UoM.=day.I am facing problem only single wbs element &network ts network PR>PO>MIGO already posted material doc.

cn41n report same error error

kindly suggest me  steps wise

BR

PRASAD

former_member228466
Participant
0 Kudos

Dear Prasad,

Apparently someone changed the units of the operation after it was partially confirmed . When they confirmed in the new unit the error started.

unconfirmed the network, then deleted the operation and saved. After that just created the operation again and confirmed the network.

Regards

Soni

former_member228466
Participant
0 Kudos

Dear Prasad,

Also check what is the UOM maintained for activity type.

Regards

Soni