Hi Gurus,
I am working on PS-PM Integration for shutdown process and I am consultant of PM.
Client requirement is PM orders (subnetwork) need to schedule in Background whenever Project schedule instead of using CN24N.
I am looking for BAdi for this process and kindly share solution regarding this process for BAdi or any other alternative way.
Singh.
Hello Singh
There is no Badi or bapi to do this,
CN24N is a top-scheduling tool regarding PM orders.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Swapnil,
Thanks for giving responce.
Actually client thinking it is doubling of work for rescheduling of Orders.
i.e. first schedule the Project and next Using of CN24 for Order dates scheduling according to current project dates.
I studied earlier that, through BADi we can control data exchange between Activity and Subnetwork.
Now I racalled those words and trying for possibility.
Singh