Hi all,
I am using a workcenter in a project. In the workcenter I have formula SAP008 and Distribution key SAP020. When I run CM01 report, I am not getting the capacity requirement distributed. Its showing the overall capacity on the current date.
Can someone help me please.
Thanks
ANjali
Hi Anjali,
Please check if different distribution key is entered in activity.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Even check the costing tab wherein activity type as machine and labour are which formula that is concern to project/network as it should be sap004 for both entry.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Capacity will be distributed based on schedule dates. Also check what is the scheduling formula you have used in scheduling tab of work center. It should be SAP004 for internally processed activities.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.