on 01-21-2013 1:56 PM
I am just trying to clarify how a supplier would typically notify actual events, eg PO acknowledgement, PO confirmation, generation of ASN, in a 'procure to pay' scenario? Would this typically be via the WCL?
Thanks for any advice on this...
Hi,
i think this depends on your agreement with the supplier.
ASN i would say its automatically generated when updating the delivery and the sending the event per Event Type from the ERP system.
PO Acknowledgement could be the Web UI or also an Event Type by changing the PO.
But in EM you could use the Web UI, IDOCs, Webservices or directly BAPI calls so you are very flexible.
Best regards,
Steffen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes this should be also an option. I just checked our scenario description for the pre delivered Procurement scenario:
For Acknowledgement:
There are several ways for an acknowledgement to be received from the supplier. In this
scenario, we will simulate having received the acknowledgement by fax or e-mail and we will
therefore enter the supplier’s information directly in SAP ECC, accepting the PO and verifying the
quantity and delivery date. If there is a discrepancy in the delivery date or quantity, or both, or if
an acknowledgement is not received by the expected time, an exception message is sent to the
buyer.
Web transactionwould be also an option.
For ASN:
In this step, the ASN receipt is simulated by creating an inbound delivery directly in SAP ECC.
Note that it is also possible to receive the ASN either electronically (via IDoc) or using a standard
Web transaction.
We use the option with the inbound delivery but the other ones are also common according to this.
Best regards,
Steffen